LADWP - Feed-in Tariff (FiT) Program

Last updated: June 03, 2019

Program Overview

Implementing Sector:Utility
Category:Financial Incentive
State:California
Incentive Type:Feed-in Tariff
Web Site:https://www.ladwp.com/fit
Start Date:02/01/2013
Utilities:Los Angeles Department of Water & Power
Eligible Renewable/Other Technologies:Solar Photovoltaics
Incentive Amount:$0.17/kWh adjusted by a time of delivery multiplier Base price will step down over time as certain MW goals are met
Maximum Incentive:$0.3825/kWh
Eligible System Size:30 kW - 3 MW DC
Duration:Up to 20 years
Equipment Requirements:Project must be registered as RPS-compliant with the California Energy Commission
Installation Requirements:Commercial operation must be no later than 18 months following the execution of the contract
Ownership of Renewable Energy Credits:LADWP

Summary

Note: LADWP accepted applications for the fifth allocation of the 100 MW FiT Set Pricing Program in March 2015. This program is the first component of a 150 megawatt (MW) FiT Program, and is designed to support 100 MW. The full 100 MW of contracts will be offered in five allocations occurring every six months. A plan for the additional 50 MW program is still in development. See the website above for more information.

LADWP is providing a Feed-in Tariff (FiT) program to support the development of solar photovoltaic (PV) in its territory. Project must be registered as RPS-compliant with the California Energy Commission to be participate.

The full 100 MW of contracts awarded through this program will be offered in five allocations occurring every six months. For each allocation, 4 MW of capacity will be reserved for small projects between 30 kW and 150 kW. If the small projects reach their reserved capacity limit before the total reserved capacity is met for a Tier, the remaining small projects will qualify under the total reserved capacity allocation until that category is exhausted. During the first five business days of each application period, all submitted applications will be prioritized on the FiT Reservation List by lottery. Applications received after the first five business days will prioritized in the order they are received.

The amount LADWP will pay for each kilowatt-hour (kWh) produced will be a product of the Base Price of Energy (BPE) multiplied by the appropriate Time-of-Delivery (TOD) Multiplier. The BPE is scheduled to decline as each 20 MW allocation is subscribed. The TOD multiplier varies by time of day and time of year with the highest multiplier being available between 1:00 PM and 5:00 PM during June through September. The full schedule for BPE prices and TOD multipliers can be seen in the tables below.

Base Price of Energy

Tier Level Total MW Capacity Reserved Small Project MW Capacity Reserved Pricing (per kWh)
1 0-20 0-4 $0.17
2 20-40 4-8 $0.16
3 40-60 8-12 $0.15
4 60-75 12-16 $0.14
5 75-100 16-20 $0.13

 

Time of Delivery Multiplier 

  High Peak Low Peak Base
Period M-F (1:00 pm - 5:00 pm)

M-F (10:00 am - 1:00 pm)

M-F (5:00 pm - 8:00 pm)

M-F (8:00 pm - 10:00 am)

All day Saturday and Sunday

High Season (Jun - Sep)

2.25 multiplier 1.10 multiplier 0.50 multiplier
Low Season (Oct - May) 1.30 multiplier 0.90 multiplier 0.50 multiplier

Program participants must pay application fees, interconnection study fees, development security deposits, and interconnection fees. These fees and additional program requirements can be found at the web site above.

 

Solar system price checker

Design Your Solar Home

START

Market Trend

12 3

Input your address to see if it is solar friendly and how much you can save with solar.

Great. Your address is perfect for solar. Solar incentive is still available. Select monthly utility cost and calculate the size of solar system you will need now.

Whoa ! Going solar is definitely a smart decision.

kw System size years Payback period Lifetime savings

No money down, 100% finance is available.

Use the California Sun to Power Your Home and Switch to Solar Today

Do not show this information again.